[Federal Register Volume 80, Number 112 (Thursday, June 11, 2015)]
[Notices]
[Page 33265]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-14275]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 14654-000]


Twain Resources, LLC; Notice of Preliminary Permit Application 
Accepted for Filing and Soliciting Comments, Motions To Intervene, and 
Competing Applications

    On December 12, 2014, Twain Resources, LLC, filed an application 
for a preliminary permit, pursuant to section 4(f) of the Federal Power 
Act (FPA), proposing to study the feasibility of the Tungstar Redux 
Water Power Project (Tungstar Redux Project or project) to be located 
at Pine Creek Mine and along Morgan and Pine Creek, near the City of 
Bishop in Inyo County, California. The sole purpose of a preliminary 
permit, if issued, is to grant the permit holder priority to file a 
license application during the permit term. A preliminary permit does 
not authorize the permit holder to perform any land-disturbing 
activities or otherwise enter upon lands or waters owned by others 
without the owners' express permission.
    The proposed project would consist of the following: (1) An intake 
of an unspecified design collecting Pine Creek Mine discharge water 
from its discharge point on Morgan Creek; (2) an 18-inch-diameter steel 
penstock of unspecified length with a 450-foot vertical drop: (3) A 
powerhouse: (4) a 600-kW impulse turbine connected to a 625-kVA 
generator; (5) a transmission line; (6) a substation connecting to an 
existing 56-kV main transmission line, and (7) appurtenant facilities. 
The estimated annual generation of the Tungstar Redux Project would be 
3,600 megawatt-hours.
    Applicant Contact: Mr. Doug Hicks, Twain Resources, LLC, 280 
Florenca Way, Reno, Nevada 89511; phone: (775) 997-3429.
    FERC Contact: Joseph Hassell; phone: (202) 502-8079: email 
joseph.hassell@ferc.gov.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Competing applications and notices of intent must meet the requirements 
of 18 CFR 4.36.
    The Commission strongly encourages electronic filing. Please file 
comments, motions to intervene, notices of intent, and competing 
applications using the Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief 
comments up to 6,000 characters, without prior registration, using the 
eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You 
must include your name and contact information at the end of your 
comments. For assistance, please contact FERC Online Support at 
FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE., 
Washington, DC 20426. The first page of any filing should include 
docket number P-14654-000.
    More information about this project, including a copy of the 
application, can be viewed or printed on the ``eLibrary'' link of 
Commission's Web site at http://www.ferc.gov/docs-filing/elibrary.asp. 
Enter the docket number (P-14654) in the docket number field to access 
the document. For assistance, contact FERC Online Support.

    Dated: June 5, 2015.
 Kimberly D. Bose,
 Secretary.
[FR Doc. 2015-14275 Filed 6-10-15; 8:45 am]